华润电力新增干煤棚项目施工组织设计(附答辩记录,cad图纸)(含选题审批表,任务书,开题报告,中期检查报告,毕业论文30000字,答辩记录,cad图纸4张)
摘 要: 根据合同要求,结合实际情况,编制实施性施工组织设计,制定合理的施工计划,安排施工顺序;建立以项目经理部为核心的文明安全施工领导组织,组成以项目经理为首的分级负责的安全生产体系,保障安全,文明施工。其主要内容有:工程概况、施工部署、现场平面布置、主要分部分项工程施工方案、进度计划及保证措施、质量目标及保证措施、安全保证措施、现场文明施工。
关键词:施工部署;施工方案;进度;质量目标;安全文明施工
China resources power new dry coal shed project construction design Student: Peng Li
Abstract: According to the request of the contract and on the basis of the fact, the construction enterprise institutes the implement construction planning and scheduling document, formulates the reasonable construction plan, and arranges construction sequence .The project management is the core of the leadership organization. And the project manager is the head of graduation responsible safety in the production system. The project management system must ensure safety and civilization to construct. Its main content includes: project survey, construction deployment, scene plane arrangement, main branch sub-item project construction design, progress plan and guarantee measure, quality goal and guarantee measure, safe guarantee measure, and scene civilization construction.
Keywords: Construction deployment; Construction plan; Progress; Quality goal; Safe and Civilized construction
工程概况
本工程为广东省华润电力(兴宁)有限公司2×135MW燃煤发电机组,新增干煤棚设计、制造及安装建筑工程。
工程地点:广东省兴宁市龙北镇。
工程规模和性质:广东省华润电力(兴宁)有限公司一期规模为2×135MW 燃煤发电机组,并预留扩建二期2×300MW 煤矸石燃煤发电机组的条件。50000T干煤棚建筑 工程是该项目一期的新增工程。
具体内容如下:新增干煤棚的设计及施工图纸、土建工程和钢结构雨棚的制作与安装工程(包括配套电气工程、消防工程及给排水工程)。
工程质量要求:设计、施工和完成的工程完全遵守中国现行的规范、技术标准,建筑、施工和环保规定及有关类似容量、范围及性质的发电厂的规定。签订合同后,如果国内的规范、技术标准或规定作了重大修改,或颁发新的国家规范标准,则我单位严格遵守新的规定,规范标准有不一致的地方,按照从高、从严原则执行。保证工程质量要求为优良等级。
工程技术条件:本工程位于兴达电厂原干煤棚西南侧围墙外,建筑面积约8000m²,为轻型屋架钢结构干煤棚,净空高度10.0m。基础采用柱下独立砼基础伸入到坚实稳定的老土基层,上部承重立柱采用钢构造柱(如圆柱体、H型钢等),地面以上用φ159×6无缝钢管制作安装防御车辆等意外撞击造成柱体变形的防撞笼。柱距10.0m,跨度向总长100.0m,单跨距50.0m。屋面采用760型压型彩钢板(蓝色),防雨棚外沿需设置截水槽将雨水引流至溢水沟排出,干煤棚底部待平整碾压密实后用煤矸石铺垫0.5m,干煤棚南、西、北面需布设1.0m高钢筋砼挡煤墙,再用砖砌1.0m加高至2.0m,周围用砖砌煤水沟。煤棚内在顶部安装照明设备并设置消防用水喷淋装置,原干煤棚西侧围墙的拆除与改建按现有围墙标准建设。
|